Category: News

  • 05
    Apr

    Progress update at Harrogate Bus Station

    Night shift at Harrogate Bus Station to lay ducts whilst the buses weren’t running.  ACS has been working with Centrica and Transdev to complete the installation of an electric bus charging station at Harrogate Bus Station.  This is the first of its kind in the UK to utilise ‘opportunity...

    Read More
  • 23
    Mar

    International Safety Award with Merit

    News release  23rd March 2018  ACS Construction Group Ltd and the Hull University project is presented with International Safety Award for protecting its employees from the risk of injury and ill health at work.  ACS Construction Group Ltd and the Hull University project has won an International Safety Award...

    Read More
  • 17
    Jan

    Latest Vacancies

    Due to recent contracts secured, ACS are currently recruiting for the following trades; groundworkers, pipe layers and machine drivers for contracts in the North West, North East and Yorkshire regions.  Must hold the relevant qualifications. For more info and to submit your CV, please email info@acsconstructiongroup.com  

    Read More
  • 10
    Jan

    Cardinal Maritime Handover

    ACS Construction Group is delighted that its Build and Civil Engineering divisions have handed over a new warehouse and office facility for Cardinal Maritime Ltd at Sharston Manchester. Works were completed on time with phased handovers to assist our client allowing early access to the building. This full design...

    Read More
  • 21
    Dec

    Block E slab rebar fixing

    Block E Slab Rebar Fixing progressing safely and on programme at Hull University. Block E will be poured in two stages which will allow sectional handover to the Structural Steel Contractor.

    Read More
  • 30
    Nov

    Progress update at Hull University

    ACS has completed the groundworks and concrete raft slabs (placing over 1500m3 of concrete) to the first 4 blocks of the student accommodation, we are also on programme with the concurrent construction of the next 3 blocks. ACS and Vinci achieved the first milestone handover of the new link...

    Read More
  • 29
    Nov

    Use of ‘no-dig’ guided auger boring techniques

    Use of no-dig’ guided auger boring techniques to install 52m of 150mm diameter clay pipe under the highway on our Longbridge Flight Shed Foul Drain project.

    Read More
  • 21
    Nov

    Use of Vacuum Excavation

    Use of Vacuum Excavation to expose approximately 90m of live, buried, HV cables. The site team were awarded ‘team of the week’ on the project for safe working practices and highlighting the location of buried AIB (Asbestos Insulated Board) during the operation.

    Read More
  • 10
    Nov

    New plant arrives on site

    ACS continue to invest and are committed to keeping a modern fleet for plant machinery.  The latest arrivals include 2 x Thwaites 9 tonne Forward Tipping Dumpers and 2 x Takeuchi Tracked Excavators.  

    Read More
  • 10
    Nov

    ACS complete design and construction project at Lee Valley Caravan Park

    ACS have completed the design and construction of the Final Phase works comprising 63 No. static caravan bases, access/service road, car park hardstandings and refuge areas along with all associated services, drainage and landscaping works at Lee Valley Caravan Park. Click here for more info about Lee Valley Caravan...

    Read More